Engineering Project Updates
2008 Flexible Pavement Project
July 25, 2008
The contract was awarded to Plote Construction, Inc. on May
19th, 2008 and the project began in June. It is expected
to be finished in August.You can view a map of the project here.
Concrete curb and sidewalk work is finished for the entire
project.
Asphalt surface removal is also finished, and paving is
complete on all streets except for the Concord Point
subdivision, Tubeway, Village and Westgate. Base failure
repairs are being done on those streets, and final paving should
take place next week weather permitting.