Village of Carol Stream, IL
Home MenuVillage Projects
Capital Improvement Program (CIP)
2025 Street Resurfacing Project
2025 Street Resurfacing Project Map
The 2025 Street Resurfacing Project includes curb, sidewalk and storm sewer repairs where applicable, and then the removal and replacement of the street pavement. The contractor plans to begin construction within the next few weeks, weather permitting. They plan to finish construction by the end of August. This project encompasses approximately three miles of roadway throughout the Village.
The Contractor will be performing various forms of work on many streets throughout the Village and unforeseen circumstances such as weather and construction issues make it difficult to provide an exact date when the contractor will be performing a particular task adjacent to your home. Updates on the construction progress can be found below.
This type of construction can generate some inconveniences to residents that live adjacent to the roadway. The Contractor will be instructed to provide access to your driveway as much as possible during work operations. However, some exceptions will occur. When new concrete curb or sidewalk is replaced adjacent to your driveway, you may lose access to your driveway for seven days or more while the concrete cures. While your driveway is inaccessible, arrangements have been made to allow overnight parking on your street and nearby streets. You will not need to notify the Police Department for overnight parking on these nights. A door hanger will be placed at your front door prior to undertaking work that will limit access to your driveway. You will find that when curbs and/or sidewalks adjacent to your driveway are repaired, a section of the driveway may be damaged. The contractor will perform those driveway repairs after the installation of the new curb or sidewalk.
If you or anyone in your household has physical impairments and requires special arrangements, please call Engineering Services at (630) 871-6220.
Thank you for your patience and cooperation during this project.
Street Resurfacing Construction Updates
- The project is complete at this time.
2025 Pavement Rejuvenation Project
2025 Pavement Rejuvenation Project Map
The Village has hired American Road Maintenance to perform our annual asphalt pavement rejuvenation maintenance on several streets throughout the Village. The contractor plans to perform a majority of the work during the months of June and July. This pavement treatment is dependent on weather conditions. Application will be suspended if there is rain in the forecast and will resume when weather allows.
Although streets will remain open while the rejuvenator product is being applied and limited vehicle traffic can be accommodated, we strongly encourage motorists to avoid the work area until the work has been successfully completed in an area. If you must drive on the street during the application process, we encourage you to exit your driveway and drive through the work area slowly to avoid tracking and splattering the material on your vehicle. In addition, if you drive onto your driveway before the product has cured, it will cause tracking and staining on the driveway and sidewalk.
2025 Crackfill Project
The Village has hired Denler, Inc. to perform our annual Crackfill Project on several streets throughout the Village. The contractor plans to complete a majority of the work during the month of July. This work includes placing a fiberized asphalt material on existing cracks on the asphalt roadway surface. All streets receiving treatment will be opened to traffic at all times but minor construction delays should be expected at the location where the cracks are being filled.
