Klein Creek Stream Bank Stabilization - Section II

Print
Share & Bookmark, Press Enter to show all options, press Tab go to next option

Illini Drive to Thunderbird Trail

Webpage Last Updated: September 24, 2025

Phase II Overview

The Board of Trustees approved an agreement for Professional Engineering Services to Engineering Resource Associates, Inc. (ERA) at their meeting on March 2, 2024. 

The design began with collecting information in the field. Flags were placed (pink) along the edge of the streambank, as well as metal tags on the trees for identification. Regional Land Services (RLS) then surveyed the cross section of the stream, including trees, fences, and property corners. This was followed by Testing Service Corporation (TSC) who sampled the streambed to help estimate the quantity of sediment that will have to be removed, as well as check for any pollutants of concern.

Although the Village has an easement for "Maintaining Drainage", the 30 feet is no longer sufficient for the amount of water that flows through this stretch of Klein Creek. Therefore, the design anticipates retaining wall on both sides of the creek for the entire stretch. That retaining wall will look similar to what was installed south of Thunderbird Trail (Section I) and north of Illini Drive (Section III).

SCHEDULE

DATE DESCRIPTION OF UPDATE
2026-03-31 IEPA grant deadline to begin construction.
 Winter 2026  An Open House or Presentation to Residents is planned to occur after awarding the construction contract.
Winter 2026 Awarding a Construction Contract is anticipated early next year.
2025-09-23 ERA submitted our application for the first of two major permits required (US Army Corps of Engineers).
2025-01-20 Village Board authorized executing a grant with IEPA for up to $1,000,000 in construction funding (R-3399).
2024-03-29 The topographic survey, including wetland and tree identification, was completed.
2024-03-13 A notice was mailed to residents notifying them of the award and introducing this website.
2024-03-09 ERA and RLS began their field collection of the existing conditions that will serve as the basis for the final design.
2024-03-02 Board of Trustees approves award of an agreement for Professional Engineering Services to Engineering Resource Associates, Inc. (ERA) for the Phase II - Design.
Looking North from Thunderbird Trail
Looking Northwest from Seminole Lane
Looking North from Tomahawk Ct
Looking Southwest from Illini Drive
Looking South from Illini Drive